Private Label in 25 Days: How OEM Orders Actually Run

19 January 2026 · YSCM editorial

Buyers are usually quoted a lead time without seeing what happens inside it. Here is the sequence we run for a private-label LED order, with the days each stage takes on existing tooling.

Day 1–3 — specification lock

We confirm wattage, CCT, CRI, beam, IP rating, driver brand, cable length and packaging format against an existing SKU or a drawing. Anything that needs a new mould moves the order to a 45–60 day tooling schedule.

Day 4–7 — artwork and samples

Laser marking or silkscreen layout on the housing, colour box dieline, manual and label. We send a digital proof plus a marked-up sample photo; nothing goes to print without written approval.

Day 8–20 — production

Die casting and powder coating run first, then SMT and driver assembly, then luminaire assembly and 8-hour burn-in. Every unit is photometrically spot-checked at the end of the line.

Day 21–23 — packaging and documentation

Colour boxes, manuals and labels are packed with the goods; the document pack (DoC, test reports, packing list) is issued against the order number.

Day 24–25 — loading

Container loading photos, carton dimensions and gross weight go to the buyer before the truck leaves for Foshan or Shenzhen.

What usually causes delay

  • Artwork approval loops — each round costs 2–3 days.
  • Certification scope changes mid-order, for example adding a sensor after testing.
  • Battery documentation arriving late for solar products.

If your launch date is fixed, send the artwork with the purchase order and book the testing slot at the same time. That is usually the difference between 25 days and 40.